West Avenue Phase II

Project Phase: Design

Project Limits

The project limits will include the following areas:

  • West Avenue between 8 Street and Lincoln Road, including side streets
  • Bay Road between 14 Street and the Collins Canal
  • Alton Court between 16 Street and Lincoln Road

Scope of Work

  • Storm water drainage system, including a pump station at the western street end of Lincoln Road
  • Fire hydrants
  • Sanitary sewer main
  • Water main and service lines
  • Elevating the roadway
  • Constructing new curb, gutter and sidewalks
  • Installing new crosswalk pavers at various intersections
  • Installing new signage and pavement markings
  • Installing new protected bicycle lanes along West Avenue
  • Installing new street and pedestrian lighting and traffic signals
  • Rebuilding Alton Court between Lincoln Road and 16 Street
  • Harmonizing the new roadway elevation to existing driveways
  • Constructing a section of the Baywalk and seawall at the Lincoln Road street end
  • Installing some new landscaping on the corridor

Project Timeline

Estimated Design Start Date – Summer  2017
Estimated Design Completion Date – Winter 2017

Project Team

City of Miami Beach Senior Capital Projects Coordinator

Sabrina Baglieri 

City of Miami Beach Capital Project Coordinator
Jorge Rodriguez

Engineer of Record / Resident Project Representative

Chen-Moore and Associates

Design Consultant

CES Consultants, Inc.

Contractor

Ric- Man Construction FL, Inc.

Public Information

Heather M. Leslie
HML Public Outreach
Ph: 305.905.5876
Email: heather@hmlPublicOutreach.com