Lake Pancoast Right Of Way Improvements

 

Project Limits

Just east of Pine Tree Drive to Lake Pancoast Drive, from the Liberty Avenue Street end to just south of 26 Street. 

Scope of Work 

  • Replacing the existing water mains
  • Upgrading the existing storm water drainage
  • Repaving the roadway and installing new pavement markings
  • Replacing the existing sidewalk, curb and gutter
  • Installing new traffic and pedestrian signs
  • Improvements to Historic Neighborhood
  • Installing decorative lighting and crosswalks
  • Installing new landscaping and irrigation

Project Timeline

Start Date – March 2012

Reached Substantial Completion – May 2014

Project Team

City of Miami Beach Capital Project Coordinator 

Olga Sanchez, E.I.

Engineer of Record – CH2M HILL, Inc. 

Walt Schwarz, P.E.

Contractor – Lanzo Construction, Co.

Bob Beaty

Resident Project Representative – Atkins North America  

David Carter, P.E.

Public Information –

Jeannette Lazo

Ph: 786.531.3798

Email: jeannette@iscprgroup.com