Parkview Island Right Of Way Improvements

Project Limits

Residential streets of Parkview Island:

73 Street, Wayne Avenue, Michael Street, Gary Avenue, Bruce Street and Raymond Street.   

Scope of Work

  • Water main and service replacement
  • Repaving of roadway
  • Pavement markings and striping

Project Timeline

Start Date – Winter 2013

Completion Date – Summer 2014

Project Team

City of Miami Beach Senior Capital Project Coordinator

Humberto Cabanas

City of Miami Beach Capital Project Coordinator

Dewayne Gordon

Engineer of Record

City of Miami Beach Public Works Department

Certified Engineering Inspector

Stantec

Contractor

Metro Equipment Services

Public Information – Jeanette Gorgas, Michelle Simmons

Ph: 305.254.8598, Cell: 786.239.8862

Email: jgorgas@mrgmiami.com, msimmons@mrgmiami.com