Beachwalk II Phase I

Project Limits 

South Pointe Drive to Third Street, next to the beach dunes

Scope of Work

  • Constructing a pathway and above-ground elements
  • Installing environmentally-sensitive lighting
  • Upgrading the beach showers
  • Installing irrigation and landscaping

Project Timeline

Start Date – fall 2013

Completion Date – summer 2014

Project Team

City of Miami Beach Capital Project Coordinator

Jose Velez

Engineer of Record – Coastal Systems, International

Andres Perez, P.E. 

Contractor – TEAM Contracting

Rudy Ayan

Public Information –

Ph: 305.673.7071