Flamingo Park Tennis Center Project

Project Limits 

Flamingo Park Tennis Courts and Tennis Center

Scope of Work 

  • Demolishing and replacing the existing 17 courts
  • Installing new lighting, landscaping and irrigation
  • Building a drainage system

Project Timeline

Start Date – Summer 2012

Completion Date – Summer 2013

COMPLETED. Courts and Building open to the public.

Project Team

City of Miami Beach Senior Capital Project Coordinator

Humberto Cabañas

City of Miami Beach Capital Project Coordinator

Thais Vieira, R.A.

Engineer of Record – Wolfberg Alvarez and Partners

Rafael Labrada, R.A., LEED AP

Contractor – Pirtle Construction, Co. 

Jeff Miles, LEED AP, BD+C

Public Information –

Ph: 305.673.7071