Sanitary Sewer Force Main Installation Commerce To 11 St

Project Limits

Installation of sanitary sewer pipe on Euclid Avenue and Washington Avenue from 11 Street to Commerce Street. 

Scope of Work

The purpose of the project is to  provide a redundant system for transporting sewage through the City to the County wastewater treatment plant in Virginia Key.

Project Timeline

Start Date: July 2015

Expected Completion Date: December 2016

Project Team

This project is managed by the City’s Public Works Department.

City of Miami Beach Engineer

Bruce Mowry, Ph.D., P.E.

Contractor

David Mancini and Sons, Inc.

Public Information – Media Relations Group, LLC

Jeanette Gorgas 

786-239-8862