South Pointe Landscaping Medians

Project Limits

  • South Pointe Drive between Alton Road and the east end (at the cul-de-sac)
  • Alton Road between 1 Street and South Pointe Drive

Scope of Work

  • Clearing and grubbing of medians
  • Excavating all unsuitable soil / materials
  • Placing new soil for planting
  • Installing a new irrigation system
  • Installing electrical conduits and pull boxes
  • Planting coconut palm trees, various shrubs and ground cover

Project Timeline

August through November 2015

Project Team

City of Miami Beach Senior Capital Project Coordinator

Mina Samadi

City of Miami Beach Capital Project Coordinator

Carla Dixon

Contractor

Metro Express Inc.

CIP Public Information Specialist

Lauren Firtel

Phone: 305.673.7071

Email:laurenfirtel@miamibeachfl.gov