Venetian Islands Right of Way Improvements

Project Phase – In Construction

Overview

This neighborhood project is taking place within the right of way on three of the Venetian Islands: San Marino, DiLido and Rivo Alto. The following infrastructure upgrades have already occurred: lined the sanitary sewer lines, installed a new water main and services, installed the main line and structures for an upgraded drainage system. Crews are currently focused on the installation of six pump stations, two per island; four of them are already operational and Rivo Alto work is in progress. New decorative street lights are also part of this project; they are already functioning on San Marino and DiLido Islands, and Rivo Alto’s new lighting system is in the works.

Project Limits

  • Throughout San Marino, Dilido and Rivo Alto Islands

Scope of Work 

  • Installation of six new pump stations (two per island)
  • Replacing water mains and services
  • New stormwater drainage system and pump stations
  • Lining Sanitary Sewer Main Lines
  • Reconstructing the roadway
  • Replacing sidewalks at certain locations and installing new ramps that meet the Americans with Disabilities Act (ADA) Standards
  • New concrete valley gutter throughout
  • Installing new pedestrian lighting
  • Installing landscape at certain locations

Project Timeline

Estimated Start Date – November 2013
Estimated Completion Date – Summer 2018

Project Team

City of Miami Beach Senior Capital Projects Coordinator
Sabrina Baglieri

City of Miami Beach Capital Project Coordinator
Tony Brown

Engineer of Record / Resident Project Representative
Schwebke-Shiskin and Associates, Inc.

Contractor
Lanzo Construction, Inc.

Public Information – QCA
Isabel Gonzalez
Phone: 305.345.7269