Permit Checklist for Building – Commercial New (w/ Phased)

Menú de construcción
Permits

Los proyectos pueden requerir la aprobación de la Junta de Planificación antes de la presentación del permiso de construcción

Revisiones de planes:
Building Official Approval, Environmental, Fire, Building Compliance, Planning

Inspecciones:
Notice of Commencement – Certificate, Private Provider (Pile Log Report- Certificate, Foundation, Termite Treatment - Certificates, Slab, Under Construction - Elevation Certificate, Floodproofing Certificate - Under Construction, Columns, Beams, Framing, Columns, Drywall / Metal Lath, Trusses, Sheathing, Penetration Protection, Fire Stopping Affidavits), Preliminary Fire Safety, Final Elevation Certificate, Elevator Final, Fire Final, Final Floodproofing Certificate - Final, Planning Final, Public Works Final, Final Termite Treatment - Certificate, Final Elevation Certificate, Building Final (last inspection all others must be approved prior to scheduling).

Es posible que no se requieran todas las inspecciones enumeradas.

Documentos de construcción requeridos para presentación: planos firmados y sellados digital o electrónicamente.

Documentos de construcción Revisión del departamento
Estudio del sitio firmado y sellado Estudio topográfico/de límites Building Compliance, Planning, Fire, Public Works
Civil Plans Obras públicas
Planos arquitectónicos Building Compliance, Planning, Fire, Public Works
Planos estructurales Building Compliance
Planos eléctricos Building Compliance
Elevator plans Obras públicas
Planos Mecánicos Building Compliance
Landscaping Plans Planificación
Pool plans and/or Water Feature (as needed) Building Compliance, Planning, Fire, Public Works
Fire Protection Plans Fuego
Fire Alarm Plans Fire, Building Compliance
Life Safety Plans Building Compliance, Fire
Building Compliance Building Compliance, Fire
Estudio de árboles Estudio de árboles
  • El plano del sitio debe mostrar los retranqueos, las estructuras existentes y las propuestas, los límites de la propiedad, las dimensiones del lote y la elevación del terreno según el levantamiento topográfico. También debe incluir todas las estructuras propuestas, como cercas/muros, edificaciones auxiliares, piscina, terrazas, pasarelas, equipo mecánico, etc., según lo requiera el alcance.
  • Todas las elevaciones deben incluir lo siguiente en los valores NGVD: BFE, pendiente, pendiente ajustada, francobordo (si corresponde).
  • La revisión de los documentos de construcción puede requerir departamentos adicionales

Supporting Documents That May be Required:

Documentos de construcción Revisión del departamento
Private provider required forms Building Official
Private Provide Plan Compliance Affidavits Building Official
Private provider review comments (approval of life safety drawings) Building Official, Fire
Declaration of Restrictive Covenant (if applicable) Planificación
Hold Harmless Agreement (if applicable) Building Official, City Attorney
Smoke Control (if applicable) Fire, Building Compliance
Cálculos estructurales Building Compliance
Informe geotécnico Building Compliance
Formularios de inspectores especiales Building Compliance
Aprobación de producto con especificación de instalaciones Fire, Building Compliance, Planning for the location
Heating/Cooling Sizing Load Calculations Building Compliance
Formulario de cálculo de energía Building Compliance
Flood Emergency Operations Plan Building Compliance
Disposición de los árboles (si corresponde) Grupo de Silvicultura Urbana
Plan de protección de árboles (si corresponde) Grupo de Silvicultura Urbana
Approved Tree Permit (if applicable) Grupo de Silvicultura Urbana, Planificación
Informe de cálculos de drenaje Obras públicas
Informe de prueba de percolación Obras públicas
Obras Públicas – Hoja de cálculo de la tarifa de servicios públicos de aguas pluviales Obras públicas
Fire Flow Test Fuego
Preliminary approval from Transportation Department Obras públicas
Seawall Permit in the review stage and submitted to DERM Building Compliance
Declaración jurada de control de sedimentos y erosión en sitios de construcción Ambiental
Electric Vehicles Parking Ordinance to be followed if parking lot/space/garage will be part of the project Planificación
DRB, HPB, BO, PB recorded order or Determination of Architectural Significance (if applicable) scanned into plans after cover sheet. Planificación
Completed City of Miami Beach Commercial Zoning Data Sheet scanned into plans. Zoning Data Sheet may not be altered or modified in any way Planificación
All proposed mechanical equipment and/or allowable encroachments within required yards shall be indicated on setbacks and floor elevation. Please refer to Planning & Zoning Department for additional regulations. Planificación

Required Additional Agency Approval:

Aprobación del condado de Miami-Dade y documentos que deben incluirse:

  • DERM Air Quality
  • Drainage Well Permit from DERM (if applicable)
  • DERM Sewer Capacity Certification Letter