Liste de vérification des permis de construction – Démolition commerciale (démolition totale uniquement)

Menu du bâtiment
Permits

Les projets peuvent nécessiter l'approbation du conseil d'urbanisme avant la soumission du permis de construire

Examens du plan :
Building-Multiple Trades, Environmental, Fire, Planning,
Public Works, Urban Forestry Group

Inspections :
Notice Of Commencement – Certificate, Pile Log Report- Certificate, Foundation, Termite Treatment - Certificates, Slab, Under Construction - Elevation Certificate, Floodproofing Certificate - Under Construction, Columns, Beams, Framing, Columns, Drywall/Metal Lath, Trusses, Sheathing, Penetration Protection, Fire Stopping Affidavits, Preliminary Fire Safety, Final Elevation Certificate, Elevator Final, Fire Final, Final Floodproofing Certificate - Final, Planning Final, Public Works Final, Final Termite Treatment - Certificate, Final Elevation Certificate, Building Final (last inspection all others must be approved prior to scheduling).

Toutes les inspections énumérées ne sont peut-être pas requises.

Required Construction Documents for Submittal: Digitally or Electronically Signed and Sealed Drawings.

Documents de construction Examen du département
Relevé de site Relevé topographique/limites signé et scellé Building-Multiple Trades, Fire, Planning, Public Works
Plans architecturaux Building-Multiple Trades, Fire, Planning, Public Works
Life Safety Plans Building, Fire
Enquête sur les arbres Groupe de foresterie urbaine
  • Site Plan must show setbacks, both existing and proposed structures, property lines, lot dimensions, and grade elevation as per survey. It must also include all proposed structures such as fences/walls, accessory buildings, pool, decks, walkways, mechanical equipment, etc. as may be required for scope.
  • All elevations must include the following in NGVD values: BFE, Grade, Adjusted Grade, Freeboard (if applicable).
  • Review of construction documents may require additional departments

Supporting Documents That May be Required:

Documents de construction Examen du département
DRB, HPB, BOA recorded order or Determination of Architectural Significance (if applicable) Planification
Utility disconnect letters to include FPL, Gas, Water & Sewer Electrical, Plumbing, Public Works
Dust control procedure (letter from contractor) Environnement
Disposition des arbres (le cas échéant) Groupe de foresterie urbaine
Plan de protection des arbres (le cas échéant) Groupe de foresterie urbaine
Approved Tree Permit (if applicable) Groupe de foresterie urbaine, planification
Public Works – Right of Way Permit Travaux publics
Déclaration sous serment relative au contrôle des sédiments et de l'érosion sur les chantiers de construction Environnement

Required Additional Agency Approval:

Miami-Dade County Approval and Documents to include: DERM Air Quality