GO Bond 2018 Project

Biscayne Point Canal Waterway Dredging

Project Overview:

The City is working to restore navigability throughout the Biscayne Point canal system by removing invasive plant species and accumulated sediment, conditions that were significantly worsened by Hurricane Irma in 2017. The reduced water depth has limited boat access for residents and has made portions of the canals difficult to navigate.

This project will conduct maintenance dredging in shallow sections of the waterways to re-establish safe and reliable navigation. The goal is to achieve a minimum depth of –7 ft NAVD, improving safety and access for recreational vessels.

New Updates
  • DERM permits and FDEP exemptions have been issued. The consultant is currently in active negotiations with the USACE and permit issuance is anticipated Summer 2026. The Invitation to Bid (ITB) process will commence following issuance of the USACE permits.
Past Updates
Public Meetings

 

Photo Gallery

Location

Questions?

Reach out for more information.

Project Staff

Department Lead
Capital Improvement Projects (CIP)

Department Director
David Gomez

Senior Project Manager
Bryan Niedelson

Project Manager
Larissa Vargas

Point of Contact
Nicholas Levy
NicholasLevy@Miamibeachfl.gov

Consultants (if applicable)
Cummins Cederberg

Funding

Funding

Total Budget: $6.25M

Project Status

Project Status: Permitting

Expected completion date: 2027

Last updated:

April 2026